| Role | Agency | Description | Vehicle | Obligated | Action date | Period |
|---|---|---|---|---|---|---|
| Subcontractor | General Services Administration | INSTALL SHEET PILES AND STONE COLUMNS GRAZEL FOUNDATION Parent award context Parent award agency: General Services Administration · Public Buildings Service Parent award NAICS: 236220 Parent award performance state: PR Parent award description: CBP MAYAGUEZ MARINE UNIT NEW CONSTRUCTION OF ADMINISTRATIVE BUILDING, BOAT MAINTENANCE, STORAGE HANGAR AND EXTERIOR VEHICLE PARKING SPACES LOCATED AT PR KM, 18.5 BOQUERON, CABO ROJO, PR 00623 View parent award on USAspending | — | $23,499 | Jun 3, 2025 | — – — |
| Subcontractor | General Services Administration | THE PROJECT CONSISTS OF A ONE STORY WAREHOUSE STRUCTURE WITH A FOOTPRINT OF 7,100 SQ-FT. FOR THIS PRELIMINARY PRICE
ONLY THE STRUCTURE WAS CONSIDERED FOR VIBRO-REPLACEMENT TREATMENT.
CONSTRUCTION SEQUENCE AND CONSIDERATIONS
THE FOLLOWING IS THE CONSTRUCTION SEQUENCE FOR THIS PROJECT:
1. GRAZEL FOUNDATION SUBMITS SHOP DRAWINGS AND SUBMITTALS FOR APPROVAL.
2. THE SITE IS STRIPPED, CLEARED AND GRUBBED BY OTHERS.
3. ANY EXISTING UTILITIES ARE REMOVED BY OTHERS.
4. THE SITE IS LEVELED AND MADE ACCESSIBLE FOR GF EQUIPMENT.
5. THE STONE COLUMN LOCATIONS ARE LOCATED IN THE FIELD BY OTHERS.
6. GF MOBILIZES TO THE SITE AND PREPARES EQUIPMENT FOR PRODUCTION.
7. GF PERFORMS PRODUCTION VR.
8. GF DEMOBILIZES FROM THE SITE AND BUILDING PAD CONSTRUCTION (FILLING, SCRAPING, ROLLING, ETC.) IS PERFORMED BY
OTHERS.
SURFACE CLEANUP: THE VR PROCESS WILL CREATE SOME SURFACE SPOILS AND POSSIBLY SOME SURFACE WATER. GF WILL DIVERT
THE SPOILS WITHIN THE WORK AREA, BUT THE GENERAL CONTRACTOR WILL BE REQUIRED TO REMOVE THE SPOILS FROM THE SITE AS
REQUIRED SO THAT THEY DO NOT AFFECT GF€„¢S WORK.
PROOF-ROLLING: THE VR PROCESS WILL DEPOSIT FINES AND LOOSEN THE WORKING SURFACE. THEREFORE, SURFACE LEVELING AND
ROLLING WILL HAVE TO BE PERFORMED FOLLOWING THE VR TO DENSIFY THE UPPER TWO TO THREE FEET OF SOIL. GF HAS NOT
INCLUDED THE COST OF REGRADING AND ROLLING.
ROCK BACKFILL: GF HAS INCLUDED THE COST OF ALL ROCK BACKFILL FOR THE VR INSTALLATION PROCESS.
QUALITY ASSURANCE AND QUALITY CONTROL PROGRAM
SHOP DRAWING: GF WILL DEVELOP AND SUBMIT A SHOP DRAWING BEFORE THE WORK IS PERFORMED, SHOWING THE STONE
COLUMN LOCATIONS. THE LOCATIONS WILL BE SURVEYED IN BY THE GENERAL CONTRACTOR.
PRODUCTION LOG: THE GF CRANE OPERATOR WILL KEEP A LOG AS THE WORK IS PERFORMED. THE LOG INCLUDES RECORDING THE
STONE COLUMN NUMBER, DEPTH, AMPERAGE, ESTIMATED STONE QUANTITY, CONSTRUCTION TIME, AND COMMENTS FOR EACH
COLUMN. A COPY WILL BE PROVIDED TO THE GENERAL CONTRACTOR AND THE OWNER€„¢S INSPECTOR DAILY.
MODULUS TEST: IF RECOMMENDED BY THE SOILS ENGINEER, GF WILL INCLUDE THE COST FOR ONE MODULUS TEST.
INSPECTION: FULL TIME INSPECTION BY A REPRESENTATIVE OF AN INDEPENDENT LABORATORY MAY BE REQUIRED BY THE
SPECIFICATIONS.
ACCEPTANCE CRITERIA
THE VR PROGRAM WILL BE CONSIDERED ACCEPTABLE UPON COMPLETION OF THE CONSTRUCTION OF THE VR PROGRAM AS
DESCRIBED IN THIS PROPOSAL, AND SHOWN ON THE SHOP DRAWING.
WARRANTY
GF WARRANTIES THAT THE PROGRAM STATED IN THIS PROPOSAL WILL BE PERFORMED FOR THE STATED PRICE SUBJECT TO THE TERMS
AND CONDITIONS PRESENTED.
FIELD LAYOUT, ACCESS, SCHEDULE
LAYOUT: THE GENERAL CONTRACTOR SHALL LOCATE ALL VR LOCATIONS IN THE FIELD.
ACCESS: THE GENERAL CONTRACTOR SHALL PROVIDE SAFE, UNINTERRUPTED ACCESS FOR GF€„¢S AND ITS SUPPLIERS€„¢ EQUIPMENT AND
MATERIAL TRUCKS OPERATING UNDER THEIR OWN POWER. THIS EQUIPMENT MAY INCLUDE CRAWLER CRANES, RUBBER TIRED LOADERS,
AND ROCK TRAILERS. THE WORKING PLATFORM SHOULD BE RELATIVELY LEVEL AND FIRM TO SAFELY SUPPORT THE EQUIPMENT.
SCHEDULE: GF ESTIMATES THAT THE VR CAN BE COMPLETED IN A 14 WEEK TIME FRAME. THIS SCHEDULE WILL BE ATTAINED
WITH ONE RIG AND WORKING ONE SHIFT OF 8 HOURS. 3930-22 Parent award context Parent award agency: General Services Administration · Public Buildings Service Parent award NAICS: 236220 Parent award performance state: PR Parent award description: CBP MAYAGUEZ MARINE UNIT NEW CONSTRUCTION OF ADMINISTRATIVE BUILDING, BOAT MAINTENANCE, STORAGE HANGAR AND EXTERIOR VEHICLE PARKING SPACES LOCATED AT PR KM, 18.5 BOQUERON, CABO ROJO, PR 00623 View parent award on USAspending | — | $600,000 | Jan 4, 2023 | — – — |