ADDISON CONSTRUCTION CO

Doing business as ADDISON CONSTRUCTION CO

CHEYENNE, WY, 82009

Unclaimed

Prime contracting experience

10 records from government sources. Past participation is not evidence of current teaming interest.

RoleAgencyDescriptionVehicleObligatedAction datePeriod
Prime
Department of Energy
Department of Energy
THE STEGALL SUBSTATION STAGE 07 PHASE 01 PROJECT TO REPLACE END OF LIFE EQUIPMENT AND INSTALLS A NEW CONTROL BUILDING.—$441,986Sep 16, 2026Sep 16, 2026 – Dec 1, 2028
Prime
Department of Energy
Department of Energy
GRAND ISLAND SUBSTATION, STAGE 08 AND SIOUX FALLS SUBSTATION, STAGE 15, STATION SERIVE UPGRADES, NEBRASKA AND SOUTH DAKOTA—$2,337,721Sep 2, 2026Sep 10, 2025 – May 31, 2027
Prime
Department of Energy
Department of Energy
CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA—$971,559Jul 16, 2026Sep 8, 2020 – Nov 30, 2023
Prime
Department of Energy
Department of Energy
EAGLE BUTTE SUBSTATION, STAGE 03, SOUTH DAKOTA—$847,627Dec 16, 2025Apr 12, 2024 – Jan 31, 2026
Prime
Department of Energy
Department of Energy
GROTON SUBSTATION, STAGE 15, SOUTH DAKOTA—$1,642,792Dec 8, 2025Sep 22, 2023 – Jan 9, 2026
Prime
Department of Energy
Department of Energy
NORTH CODY MOI 954 SWITCH REPLACEMENT - WESTERN AREA POWER ADMINISTRATION (WAPA) ROCKY MOUNTAIN REGION HAS A REQUIREMENT WITH THE PRINCIPLAL COMPONENTS OF WORK TO INCLUDE REPLACING ONE (1) 115-KV, 1200-AMP MOTOR-OPERATED INTERRUPTER (ALSO REFERRED TO—$521,721Sep 16, 2025Sep 16, 2025 – Sep 30, 2027
Prime
Department of Energy
Department of Energy
HOYT AND KIOWA CREEK 115-KV BREAKER REPLACEMENT—$770,564May 1, 2025Aug 9, 2022 – May 1, 2025
Prime
Department of Energy
Department of Energy
LIBERTY SUBSTATION - STATION SERVICE UPGRADES, CONTRACTOR TO AQUIRE AND INSTALL VARIOUS ELECTRICAL EQUIPMENT ITEMS. SEE SPEC FOR DETAILS—$1,285,274Nov 29, 2024Sep 20, 2022 – Sep 5, 2024
Prime
Department of Energy
Department of Energy
AULT-BADWATER-NORTH CODY EQUIPMENT INSTALL—$488,215Oct 24, 2023May 6, 2020 – Jan 15, 2023
Prime
Department of Energy
Department of Energy
KIMBALL SUBSTATION STAGE 04—$252,584Sep 2, 2022Sep 24, 2020 – Sep 4, 2022

Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.

Agencies supported

  • Department of EnergyGov-sourced
ADDISON CONSTRUCTION CO – Cheyenne, WY | UEI D4N8K3L9E824 | FedSub