← Back to search
WG TOMKO INC
FINLEYVILLE, PA, 15332
Unclaimed
Subcontracting experience
1 record from government sources. Past participation is not evidence of current teaming interest.
| Role | Agency | Description | Vehicle | Obligated | Action date | Period |
|---|---|---|---|---|---|---|
| Subcontractor | Department of Health and Human Services | • CAMERA AND ROD OUT UNDERGROUND SEWER TO THE NEAREST MANHOLE.
• UNDERGROUND PVC SANITARY TO POINTS OF CONNECTION TO THE EXISTING SYSTEM CURRENTLY SHOWN ON THE PLUMBING DRAWINGS.
• UNDERGROUND SITE GAS PIPING FROM THE BUILDING TO THE GENERATOR.
• ABOVE GROUND PVC SANITARY, WASTE AND VENT PIPING.
• ABOVE GROUND COPPER DOMESTIC HOT AND COLD-WATER PIPING.
• ABOVE GROUND CPVC REVERSE OSMOSIS DEIONIZED WATER PIPING.
• ABOVE GROUND BLACK STEEL NATURAL GAS PIPING.
• ABOVE GROUND COPPER LABORATORY AIR, NITROGEN, AND VACUUM PIPING.
• ABOVE GROUND 3/8” STAINLESS STEEL TUBING FOR BREATHABLE AIR PIPING.
• ALL LABORATORY EQUIPMENT WILL BE SUPPLIED, OFF-LOADED, AND SET IN PLACE BY OTHERS WITH FINAL CONNECTIONS BY SUBCONTRACTOR.
• ONE (1) JOB-SITE MOBILIZATION • ACT 45 SALES TAX
• PLUMBING FIXTURES • FIXTURES SUPPORTS
• FLOOR DRAINS • CLEANOUTS
• BACKFLOW PREVENTERS • SHOCK ABSORBERS
• MIXING VALVES • TRAP PRIMERS
• FLOOR DRAIN FLASHINGS • ACCESS PANELS
• WATER HEATERS • EXPANSION TANK
• RECIRCULATING PUMP • AQUASTAT
• REVERSES OSMOSIS DEIONIZED WATER SKID(BOD) • NITROGEN GENERATOR(F&I) (14 WEEKS)
• PRESSURE GAUGES & THERMOMETERS • GAS PRESSURE REGULATORS
• PIPE IDENTIFICATION • PIPE INSULATION
• CORE HOLES • FIRE-STOPPING
• EXCAVATION, BEDDING AND BACKFILL • BUY AMERICAN PER FAR 52.225-9
• DAVIS BACON WAGES INCLUDING CERTIFIED PAYROLL
CLIN 0001:
• FURNISH AND INSTALL (1) ROOFTOP UNIT (34-36 WEEKS)
• FURNISH AND INSTALL (4) SPLIT SYSTEMS
• FURNISH AND INSTALL (1) LAB EXHAUST FAN (27 WEEKS)
• FURNISH AND INSTALL (2) EXHAUST FANS
• FURNISH AND INSTALL (3) FAN FILTER UNITS
• FURNISH AND INSTALL (19) VARIABLE VOLUME BOXES
• FURNISH AND INSTALL (5) SUPPLY AIR VALVES WITH HOT WATER COIL
• FURNISH AND INSTALL (8) EXHAUST AIR VALVES
• FURNISH AND INSTALL (3) FUME HOOD VALVES
• FURNISH AND INSTALL (3) BOILERS
• FURNISH AND INSTALL (2) HOT WATER PUMPS
• FURNISH AND INSTALL (1) AIR SEPARATOR
• FURNISH AND INSTALL (1) EXPANSION TANK
CLIN 0002:
• FURNISH AND INSTALL (2) ROOFTOP UNITS (26 WEEKS)
• FURNISH AND INSTALL (1) VARIABLE VOLUME BOX
• FURNISH AND INSTALL (3) SUPPLY AIR VALVES WITH HOT WATER COIL
• FURNISH AND INSTALL (2) EXHAUST AIR VALVES
• FURNISH AND INSTALL (8) FUME HOOD VALVES
• REFRIGERANT PIPING • ONE (1) JOB SITE MOBILIZATION
• MINIMAL DEMOLITION IF NECESSARY • CONDENSATE DRAIN PIPING
• NEW DUCTWORK AND ACCESSORIES • HOT WATER PIPING
• FIRE DAMPERS AS SHOWN • CONTROL DAMPERS AS SHOWN
• GRILLES, REGISTERS AND DIFFUSERS
• COMMISSIONING ASSIST • BACKDRAFT DAMPER AS SHOW
• TESTING, ADJUSTING AND BALANCING
• EQUIPMENT IDENTIFICATION • AUTOMATIC TEMPERATURE CONTROLS BY SIEMENS
• DUCTWORK AND PIPING INSULATION • START-UP OF OUR EQUIPMENT
• FIRE STOPPING AS REQUIRED • DUCT MOUNTED SMOKE DETECTORS
• TEMPORARY FILTERS AS REQUIRED • BOND SVI-2319063-WGT Parent award context Parent award agency: Department of Health and Human Services · Centers for Disease Control and Prevention Parent award NAICS: 236220 Parent award performance state: PA Parent award description: PITT B141 View parent award on USAspending | — | $4,338,000 | Nov 2, 2023 | — – — |
Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.