← Back to search

CARLISLE CONSTRUCTION, LLC

PINE MOUNTAIN, GA, 31822

Prime contracting experience

43 records from government sources. Past participation is not evidence of current teaming interest.

RoleAgencyDescriptionVehicleObligatedAction datePeriod
Prime
Department of Defense
Department of the Army
REPLACE ROOFS BLD 2785, 2818, 9049, 9097W911SF20D0003USAspending$2,869,000Jul 23, 2026Sep 19, 2024 – Sep 21, 2026
Prime
Department of Defense
Department of the Army
IAW SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REMOVE AND INSTALL NEW HVAC EQUIPMENT, INCLUDING (3) AIR HANDLING UNITS, (5) MAKE-UP AIR UNITS, (2) PUMPS, AND ALL HVAC CONTROLS B2943W911SF20D0003USAspending$997,147Jul 23, 2026Jun 3, 2025 – Nov 16, 2026
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REPLACE THE EXISTING 2 PIPE BOILER/CHILLER FAN COIL SYSTEM WITH A WATER SOURCE HEAT PUMP SYSTEM.W911SF20D0003USAspending$2,080,000Jul 20, 2026Sep 19, 2025 – Apr 30, 2027
Prime
Department of Defense
Department of the Army
IAW WITH THE ATTACHED SOW, THIS PROJECT CONSISTS OF REPLACING THE EXISTING METAL ROOF IN ENTIRETY AND MAKING NECESSARY REPAIRS OF ALL DEFICIENCIES IN CONJUNCTION WITH THE ROOF REPLACEMENTS.W911SF20D0003USAspending$675,145Jul 13, 2026Jul 13, 2026 – Aug 12, 2027
Prime
Department of Defense
Department of the Army
IAW THE SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO ADD FANS AND EXHAUST TO PROMOTE BETTER AIR MOVEMENT THROUGHOUT THE BUILDING.W911SF20D0003USAspending$912,120Jul 13, 2026May 1, 2025 – Sep 24, 2026
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW, THIS PROJECT CONSISTS OF REPLACING THE EXISTING METAL ROOF IN ITS ENTIRETY DOWN TO THE ROOF DECKING AND FURRING AND MAKING NECESSARY REPAIRS OF ALL DEFICIENCIES IN CONJUNCTION WITH THE ROOF REPLACEMENT.W911SF20D0003USAspending$394,945Jul 7, 2026Jul 7, 2026 – Jul 5, 2027
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW THE PROJECT CONSISTS OF REPAIRING THE TOWER LOCATED AT CACTUS RANGE. THE CONTRACTOR WILL DEMOLISH THE EXISTING TOWER DOWN TO THE BARE METAL STRUCTURAL MEMBERS AND CONCRETE SLAB AND REPLACE/REPAIR ALL OTHER ELEMENTS.W911SF20D0003USAspending$419,890Jul 7, 2026Jul 7, 2026 – Jul 1, 2027
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW, RENOVATE EXISTING LATRINE/SHOWER, ADD A NEW LATRINE WITH LAUNDRY, REPLACE BROKEN OVERHEAD DOOR, ADD 240V OUTLET, INFILL TWO WINDOWS AND ONE EXTERIOR DOOR, UPDATE INTERIOR AND EXTERIOR FINISHESW911SF20D0003USAspending$455,263Jun 14, 2026Sep 17, 2025 – Aug 13, 2026
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW, THE PROJECT CONSISTS OF REPLACING ALL THE STRAIGHT MISSION BARREL TILE WITH A MINIMUM 50-YEAR MANUFACTURERS LIMITED WARRANTY FOR BUILDING 130 IN ENTIRETY.W911SF20D0003USAspending$1,849,000May 28, 2026May 29, 2026 – Jul 23, 2027
Prime
Department of Defense
Department of the Army
IAW THE SOW, THE PROJECT CONSISTS OF REPLACING UP THE ENTIRE EXISTING PVC ROOFING SYSTEM WITH NEW 80 MIL ROLLED GOODS PVC FLAT ROOF FROM A SINGLE SOURCE MANUFACTURER WITH A 20-YEAR NDL, NO DOLLAR LIMIT WARRANTY.W911SF20D0003USAspending$542,200May 28, 2026Jun 1, 2026 – Apr 27, 2027
Prime
Department of Defense
Department of the Army
IAW WITH ATTACHED SOW: THIS PROJECT WILL UPDATE SEVERAL INTERIOR AND EXTERIOR REPAIRS TO THE MENTIONED RANGE SHED FACILITIESW911SF20D0003USAspending$956,177May 13, 2026Sep 19, 2025 – Jul 27, 2026
Prime
Department of Defense
Department of the Army
ROOFS REPAIR B2506, 2507, 2509, 385W911SF20D0003USAspending$1,048,000Apr 22, 2026Sep 1, 2024 – Jun 8, 2026
Prime
Department of Defense
Department of the Army
PROPANE PLANT REPAIRS (PROJECT #44252)W911SF20D0003USAspending$1,496,935Apr 21, 2026Aug 31, 2023 – Aug 21, 2026
Prime
Department of Defense
Department of the Army
THE PROJECT CONSISTS OF REPLACING THE EXISTING FAILING ASPHALT ROOF SYSTEM IN ENTIRETY, REPLACING THE ROTTEN SOFFITS AND FASCIA, REPLACING GUTTER AND DOWNSPOUT SYSTEMS, AND OTHER REPAIRS TO EXTERIOR DEFICIENCIES IN BUILDINGS 15, 16, 45, AND 74 AT CFMW911SF20D0003USAspending$458,800Mar 4, 2026Jun 30, 2025 – Jul 6, 2026
Prime
Department of Defense
Department of the Army
CONSTRUCT OH CANOPY LAAF M6141, M6144W911SF20D0003USAspending$668,000Mar 4, 2026Sep 23, 2024 – Jun 22, 2026
Prime
Department of Defense
Department of the Army
WTC REPAIR TRAINING SHEDSW911SF20D0003USAspending$849,800Jan 23, 2026Aug 30, 2024 – May 12, 2026
Prime
Department of Defense
Department of the Army
MAIDIQ CONSTRUCTION FORT BENNINGW911SF20D0003USAspending$271,680Jan 14, 2026Sep 6, 2024 – Feb 27, 2026
Prime
Department of Defense
Department of the Army
REPAIR FIRE ALARM SYSTEM, BARRACKS, B914W911SF20D0003USAspending$1,084,289Dec 19, 2025Jun 3, 2024 – Feb 13, 2026
Prime
Department of Defense
Department of the Army
IAW THE SCOPE OF WORK: THE OBJECTIVE OFW911SF20D0003USAspending$315,500Dec 18, 2025Sep 26, 2024 – Dec 31, 2025
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW, REPAIR ROADS AT CAMP MERRILLW911SF20D0003USAspending$747,845Sep 18, 2025Sep 19, 2025 – Oct 19, 2026
Prime
Department of Defense
Department of the Army
IAW THE SOW ATTACHED: THE PROJECT CONSISTS OF REPLACING THE EXISTING FLAT AND METAL ROOF SYSTEM FOR BUILDING 20 IN ENTIRETY AND TO MAKE NECESSARY REPAIRS OF ALL DEFICIENCIES IN CONJUNCTION WITH THE ROOF REPLACEMENTSW911SF20D0003USAspending$385,546Aug 6, 2025Aug 7, 2025 – Jul 3, 2026
Prime
Department of Defense
Department of the Army
REPAIRS TO FOUNTAINS MWH B4W911SF20D0003USAspending$922,000Jul 17, 2025Sep 18, 2024 – Jul 16, 2026
Prime
Department of Defense
Department of the Army
THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REPLACE THE EXISTING FIELD CONTROLLERS, COMMUNICATIONS TRUNK AND INTEGRATE ALL POINTS INTO THE UMCS.W911SF20D0003USAspending$336,400Jul 9, 2025Jun 6, 2025 – Aug 4, 2026
Prime
Department of Defense
Department of the Army
REPAIR MOVER TARGET SHEDS CARMOUCHEW911SF20D0003USAspending$393,224Jul 1, 2025May 13, 2024 – Sep 1, 2025
Prime
Department of Defense
Department of the Army
REPIR HVAC, INSTALL HIGH SPEED DOORS PARW911SF20D0003USAspending$394,900Apr 28, 2025Sep 19, 2024 – Oct 1, 2025
Prime
Department of Defense
Department of the Army
IAW THE ATTACHED SOW: THE PROJECT CONSISTS OF REPAIRING THE TOWER LOCATED AT PORTER RANGE. THE CONTRACTOR WILL DEMOLISH THE EXISTING TOWER DOWN TO THE BARE METAL STRUCTURAL MEMBERS AND REPLACE/REPAIR OR REMOVE AND REINSTALL ALL OTHER ELEMENTS.W911SF20D0003USAspending$254,254Apr 18, 2025Apr 22, 2025 – May 18, 2026
Prime
Department of Defense
Department of the Army
HVAC BLDG 2931W911SF20D0003USAspending$772,200Jan 1, 2025Aug 3, 2022 – Feb 28, 2025
Prime
Department of Defense
Department of the Army
REPAIR HVAC B5122 5123 5124 & 5130W911SF20D0003USAspending$1,269,800Oct 14, 2024May 22, 2024 – Oct 14, 2025
Prime
Department of Defense
Department of the Army
CONSTRUCT ACFT FACILITY B3270W911SF20D0003USAspending$338,300Apr 24, 2024Sep 12, 2023 – Sep 16, 2024
Prime
Department of Defense
Department of the Army
REPAIR HVAC BLDG 2882W911SF20D0003USAspending$1,724,649Dec 27, 2023Feb 7, 2020 – Feb 26, 2024
Prime
Department of Defense
Department of the Army
BLDG 368 & BLDG 398W911SF20D0003USAspending$1,147,587Oct 17, 2023Aug 3, 2022 – Apr 1, 2024
Prime
Department of Defense
Department of the Army
REPLACE PVI BOILER DFAC B3110W911SF20D0003USAspending$336,800Oct 4, 2023Jul 25, 2022 – Feb 20, 2024
Prime
Department of Defense
Department of the Army
BOILER DFAC B3235W911SF20D0003USAspending$372,850Oct 4, 2023Jul 25, 2022 – Apr 1, 2024
Prime
Department of Defense
Department of the Army
BLDG 2643&2644 REPLACE BOILERSW911SF20D0003USAspending$1,088,820Oct 4, 2023Sep 5, 2022 – Apr 1, 2024
Prime
Department of Defense
Department of the Army
REPAIR ROOF BLDG 2837W911SF20D0003USAspending$620,803Sep 15, 2023May 15, 2023 – Jan 22, 2024
Prime
Department of Defense
Department of the Army
MAIDIQ CONSTRUCTION FORT MOOREW911SF20D0003USAspending$267,800Jul 27, 2023Jun 9, 2023 – Sep 18, 2024
Prime
Department of Defense
Department of the Army
0011781791-0002W911SF20D0003USAspending$346,710Jun 13, 2023Nov 29, 2022 – Sep 29, 2023
Prime
Department of Defense
Department of the Army
REPAIR HVAC BLDG 2600W911SF20D0003USAspending$266,668May 9, 2023Apr 24, 2023 – Oct 23, 2023
Prime
Department of Defense
Department of the Army
MAIDIQ CONSTRUCTION FORT BENNINGW911SF20D0003USAspending$1,248,000Mar 20, 2023Apr 17, 2023 – Apr 16, 2024
Prime
Department of Defense
Department of the Army
BUILDING 75 LEAD BASED PAINT ABATEMENTW911SF20D0003USAspending$597,111Jan 4, 2023Jul 1, 2021 – Feb 28, 2023
Prime
Department of Defense
Department of the Army
0011813675-0001W911SF20D0003USAspending$914,777Nov 22, 2022Sep 5, 2022 – Nov 14, 2023
Prime
Department of Defense
Department of the Army
REPLACE HVAC & CHILLERSW911SF20D0003USAspending$359,750Oct 25, 2022Sep 12, 2022 – Oct 25, 2023
Prime
Department of Defense
Department of the Army
BLDG 9140-9143W911SF20D0003USAspending$1,792,655Jul 28, 2022Jul 25, 2022 – Aug 22, 2025

Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.

Agencies supported

  • Department of DefenseGov-sourced

Government-sourced data comes from SAM.gov, SBA and USAspending.gov and is attributed to its source. Items marked company-reported were provided by the company and are verified by FedSub only where labeled. FedSub is a private company and is not affiliated with SBA, GSA/SAM.gov, or any government agency.

CARLISLE CONSTRUCTION, LLC – Pine Mountain, GA | UEI KS78Z7XW2ND4 | FedSub