← Back to search

TAFT ELECTRIC COMPANY

Doing business as TAFT ELECTRIC CO

VENTURA, CA, 93003

Subcontracting experience

5 records from government sources. Past participation is not evidence of current teaming interest.

RoleAgencyDescriptionVehicleObligatedAction datePeriod
Subcontractor
National Aeronautics and Space Administration
LEAP MPK ASSY AT SLC-3
4500107410
Parent award context
Parent award agency: National Aeronautics and Space Administration · National Aeronautics and Space Administration
Parent award NAICS: 541715
Parent award performance state: CO
Parent award description: CRYOGENIC (H2-O2) SMART PROPULSION FLIGHT DEMONSTRATION
View parent award on USAspending
—$26,837Dec 9, 2025— – —
Subcontractor
Department of Defense
INSTALLATION: €¢ DEMO OF EXISTING LIGHTING AND WIRING. (CONDUIT TO REMAIN) €¢ INSTALL OF NEW LIGHTING (34 FIXTURES 6 OF WHICH ARE EMERGENCY) AND WIRING PER PHOTOMETRIC DRAWINGS. €¢ INSTALLATION OF 3 NEW EXIT SIGNS WITH EMERGENCY LIGHTING. €¢ REMOVAL AND HAUL OFF OF DEMOED LIGHTING AND WIRE. €¢ INSTALLATION OF TEMPORARY TASK SPECIFIC LIGHTING. €¢ INSTALL NEW LIGHT SWITCHES INDICATED ON GOVERNMENT SUPPLIED DRAWING.FA461020D0003USAspending$55,744Oct 15, 2024— – —
Subcontractor
Department of Defense
ELECTRICAL: BIOLOGICAL, ARCHEOLOGICAL AND NATIVE AMERICAN MONITORING WILL BE PROVIDED DURING DIGGING, TRENCHING ACTIVITIES AS REQUIRED. ALL MONITORING WILL BE COORDINATED WITH 30CES/CEIEC 6€Ͽ½8 WEEKS PRIOR TO MOBILIZATION AS REQUIRED BY THE 813. 813 PACKAGES WILL BE KEPT ON SITE FOR THE DURATION OF THE PROJECT. · TRENCH WILL BE DUG FROM NEW POWER POLE TO LOCATION OF NEW TRANSFORMER PAD TO A DEPTH BETWEEN 24€Ͽ½ AND 36€Ͽ½. EXISTING CONDUIT AND WIRE WILL BE DEMOLISHED, REMOVED AND DISPOSED OF PROPERLY. · 2 NEW 4€Ͽ½ CONDUITS WILL BE INSTALLED BETWEEN NEW POWER POLE AND LOCATION OF NEW TRANSFORMER PAD. · NEW CONDUIT WILL BE INCASED IN CONCRETE. TRENCH WILL BE BACKFILLED, COMPACTED TO 95% AND ASPHALT WILL BE PATCHED ACROSS THE ROAD. REMAINING TRENCH WILL BE BACKFILLED TO MATCH EXISTING LANDSCAPE. TRENCHING AND BACK FILL TO INCLUDE RED DYE CONCRETE TO 4€Ͽ½ ABOVE CONDUITS, BACK FILL MINIMUM 12 INCHES (NATIVE SOIL) COMPACTED TO 95% AND PATCHING ASPHALT. · ONE NEW 4€Ͽ½INCH CONDUIT WILL BE REDUCED TO 2 INCH AND SWEPT UP THE POLE TO A POWER LINE RISER COMPLETE WITH CROSS ARMS, CUTOUTS AND HARDWARE NECESSARY TO SUPPLY POWER TO NEW TRANSFORMER. NEW 12KV RISER INCLUDING ALL NECESSARY CROSSARMS, CUTOUTS, AND HARDWARE WILL BE PROVIDED AND INSTALLED. 2ND CONDUIT WILL BE CAPPED OFF AT BOTH ENDS FOR LATER USE. · NEW 7€„¢ X 7€„¢ X 6€Ͽ½ FORM FOR NEW CONCRETE FORM WILL BE INSTALLED WITH 4€Ͽ½ COMPACTED BASE AND #4 REBAR ON 18€Ͽ½ CENTER. FOUR SCHEDULE 80 STUB OUTS WILL BE INSTALLED IN PAD. (1 TRANSFORMER TO PANEL, 1 TRANSFORMER TO POLE, 2 FOR FUTURE HVAC.) 1 NEW GROUNDING ROD WILL BE INSTALLED ADJACENT TO FORM PRIOR TO CONCRETE. · WE WILL PROVIDE AND INSTALL 3000PSI CONCRETE WITH A BROOM FINISH. · WE WILL PROVIDE AND INSTALL NEW PANEL. PANEL €œA€Ͽ½ WILL BE 225 AMPS€Ͽ½BUS (COPPER), 209Y/120V, 3€Ͽ½PHASE, 4€Ͽ½WIRE WITH (42) CIRCUIT€Ͽ½BREAKERS. APPROXIMATELY 15€Ͽ½20 FEET OF POWER CABLE FROM THE END OF THE RUN WHICH WILL BE USED FOR FINAL SWITCHGEAR CONNECTIONS WILL BE INSTALLED. PROPER CONNECTIONS AND REQUIRED GROUNDING INTO THE SECONDARY SIDE OF THE PAD MOUNT TRANSFORMER WILL BE INSTALLED. DOCUSIGN ENVELOPE ID: 9F9232D2F91DF55D-D-4D1DB4D--443E2D56-9-A23927-8C-D2E156C2B39D81DF9A58A3C CONTRACTOR€„¢S INITIALS SUBCONTRACTOR€„¢S PAGE 4 OF 25 INITIALS · WE WILL PROVIDE AND INSTALL NEW 75KVA PAD MOUNT TRANSFORMER MEETING ALL REQUIREMENTS AS OUTLINED IN UFGS 33 71 02 AND UFC 3€Ͽ½550€Ͽ½01 · #2 AWG EPR, 220 MILS, 133% INSULATION (MV105) HIGH VOLTAGE WIRING WILL BE PROVIDED AND INSTALLED FROM OVERHEAD RISER TO HIGH VOLTAGE SIDE OF NEW TRANSFORMER. (FINAL CONNECTION TO BE COORDINATED WITH AND COMPLETED BY CE). 12 KV WIRE WILL BE TESTED TO INSURE IN MEETS VSFB GUIDELINES, MANUFACTURE RECOMMENDATIONS OR NETA STANDARDS. · SECONDARY POWER CABLE WILL BE PROVIDED AND INSTALLED FROM NEW TRANSFORMER TO NEW PANEL IN MECHANICAL ROOM. · EXISTING RECEPTACLES, SWITCHES AND LIGHT FIXTURES WILL BE INSPECTED. ANY RECEPTACLES, SWITCHES OR LIGHT FIXTURES DETERMINED TO BE NONOPERATIONAL WILL BE REPLACED WITH LIKE IN KIND OR EQUAL. · REPLACE EXISTING MECHANICAL ROOM DOOR WITH LIKE IN KIND OR EQUAL. DOOR TO INCLUDE HARDWARE AND 2€„¢X2€„¢ VENT.
1914-44
Parent award context
Parent award agency: Department of Defense · Department of the Air Force
Parent award NAICS: 236220
Parent award performance state: CA
Parent award description: XUMU23-2209, INSTALL ELECTRICAL POWER AT FACILITY 2002, VANDENBERG SFB, CA
View parent award on USAspending
FA461020D0003USAspending$180,673Jun 25, 2024— – —
Subcontractor
Department of Defense
SITE ELECTRICAL' BUILDING ELECTRICAL
124003-0006
Parent award context
Parent award agency: Department of Defense · Department of the Navy
Parent award NAICS: 236220
Parent award performance state: CA
Parent award description: DBB P525, NRL FACILITY REPLACEMENT?
View parent award on USAspending
N6247321D1206USAspending$16,613,499Jun 4, 2024— – —
Subcontractor
Department of Defense
INSTALL A 240 VOLT 50 AMP RECEPTACLEFA461023D0001USAspending$44,401Oct 6, 2023— – —

Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.

Government-sourced data comes from SAM.gov, SBA and USAspending.gov and is attributed to its source. Items marked company-reported were provided by the company and are verified by FedSub only where labeled. FedSub is a private company and is not affiliated with SBA, GSA/SAM.gov, or any government agency.

TAFT ELECTRIC COMPANY – Ventura, CA | UEI KE1WN1MPKJL9 | FedSub