| Role | Agency | Description | Vehicle | Obligated | Action date | Period |
|---|---|---|---|---|---|---|
| Subcontractor | General Services Administration | 1. REPLACE THE EXISTING GALVANIZED DOMESTIC WATER PIPING, FITTINGS, GAUGES AND VALVES IDENTIFIED
WITHIN THE
RFP AND DISCUSSED DURING THE OUR WALK THROUGH HELD ON TUESDAY, FEBRUARY 6TH, 2024.
2. REMOVE EXISTING GALVANIZED PIPING FOLLOWING THE NEW PIPING BEING BROUGHT ON LINE FOR USE.
3. PROVIDE DUCTWORK MODIFICATIONS WITHIN THE LOWER LEVEL IRS SPACE TO ALLOW FOR THE 8” WATER MAIN
TO BE
REPLACED. ASSIST WITH COORDINATION OF THESE SHUTDOWNS WITH BLUE SPADER, JLL AND THE GSA.
4. PROVIDE FLOOR CORING AS NEEDED FOR INSTALLATION OF NEW RISERS. AS DIRECTED VIA THE RFP OUR
PROPOSALS
ASSUMES WE CAN CORE THROUGH THE EXISTING SLAB, WE HAVE NOT INCLUDED COSTS FOR A STRUCTURAL
ENGINEER OR FLOOR SCANNING.
5. PROVIDE PLUMBING INSULATION.
6. PROVIDE CHLORINATION AND TESTING FOR OUR NEW PIPING INSTALLATIONS.
7. REMOVE AND REPLACE PRESSURE REDUCING STATIONS, GAUGES, VALVES, FITTINGS AND ACCESSORIES IN LINE
WITH THE EXISTING GALVANIZED PIPING.
8. FLUSHING VALVES AND TEST PORTS
A. FOR THE PORTION OF THE PIPING WE ARE REPLACING, WE HAVE INCLUDED A LOCKING FLUSHING VALVE /
TEST PORT AND ISOLATION VALVE TO THE 5TH FLOOR, 1ST FLOOR AND LOWER LEVEL HORIZONTAL RUNS.
B. PER OUR WALK THROUGH, WE HAVE INCLUDED A LOCKING FLUSHING VALVE / TEST PORT WITH HOSE
CONNECTION AND ISOLATION VALVE ON EVERY OTHER FLOOR OF THE RISER.
C. WE HAVE NOT INCLUDED ANY SANITARY PIPING MODIFICATIONS TO ACCOMMODATE THE FLUSH VALVES
AS DURING OUR FEBRUARY 6TH WALK THROUGH WE DISCUSSED PROVIDING A HOSE CONNECTION AT THE
FLUSH VALVE LOCATIONS THAT CAN THEN BE ROUTED TO THE NEAREST FLOOR DRAIN WITHIN THE
MECHANICAL ROOM. LIMBACH GALV Parent award context Parent award agency: General Services Administration · Public Buildings Service Parent award NAICS: 238220 Parent award performance state: MI Parent award description: GALVANIZED PIPE REPLACEMENT, ROSA PARKS BUILDING, 985 MICHIGAN AVENUE, DETROIT, MICHIGAN. View parent award on USAspending | — | $2,000,561 | Jul 29, 2024 | — – — |
| Subcontractor | General Services Administration | SCOPE OF SERVICES – DOMESTIC HOT WATER AND ELECTRIC WATER COOLER REPLACEMENT
1. PROVIDE AND INSTALL TANK LESS WATER HEATERS WITH ALL ACCESSORIES SHOWN BELOW COUNTERS AT (34) SINK
LOCATIONS WITHIN THE FACILITY.
2. PROVIDE PLUMBING MODIFICATIONS TO PIPING AS SHOWN WITHIN CONTRACT DOCUMENTS.
3. PROVIDE PLUMBING INSULATION WHERE NEW DOMESTIC WATER PIPING IS INSTALLED PER CONTRACT
DOCUMENTS.
4. REMOVE AND REPLACE (20) ELECTRIC WATER COOLERS AND CARRIERS PER CONTRACT DOCUMENTS.
ARCHITECTURAL
DEMO, FINISHES AND ELECTRICAL SERVICES BY OTHERS.
5. PROVIDE CHLORINATION OF DOMESTIC WATER SYSTEM.
6. PROVIDE WATER SAMPLING AND TESTING PER AMENDMENT MODIFICATION 0001.
7. PROVIDE COMMISSIONING SUPPORT TO OWNER PROVIDED COMMISSIONING AGENT.
SCOPE OF SERVICES – COOLING TOWER SWEEPER SYSTEM
1. PROVIDE AND INSTALL NEW COOLING TOWER SWEEPER SYSTEM SERVING 3 OF THE 7 BASINS WITHIN THE
TOWER.
2. PROVIDE AND INSTALL PUMP, FILTER AND BACK WASH TANK. OUR PROPOSAL INCLUDES THE PUMP, FILTER, TANK,
PIPING ARRANGEMENT AND NOZZLE LAYOUT INCLUDED IN THE ATTACHED DRAWINGS. THIS ARRANGEMENT ALLOWS
FOR
THE SUPPLY AND RETURN PIPING SERVING THE BASINS TO BE ISOLATED WHICH WAS REQUESTED BY GSA/JLL.
3. OUR PROPOSAL INCLUDES THE PUMP, FILTER AND 525 GALLON BACKWASH TANK PROVIDED BY RBE WHO
REPRESENTS
MARLEY COOLING TOWERS.
4. OUR PROPOSAL INCLUDES NOZZLES ON EITHER SIDE OF THE FILL WITH PIPING BELOW THE FILL.
5. PROVIDE AND INSTALL PIPING INSULATION AND HEAT TRACING PER CONTRACT DOCUMENTS. WE HAVE INCLUDED
PROVIDING THE HEAT TRACING WITH TURNOVER TO HATZEL & BUEHLER FOR INSTALLATION.
6. PROVIDE AND INSTALL WEIR PLATES AT (2) COOLING TOWERS TO ALLOW FOR TOWER BASINS TO BE ISOLATED.
7. PROVIDE PRV AND BACK FLOW PREVENTER AT MAKE-UP WATER SUPPLY TO FILTER PER CONTRACT DOCUMENTS.
SCOPE OF SERVICES – BALANCING
1. PROVIDE WATER BALANCE OF EXISTING DOMESTIC WATER SYSTEM INCLUDING THE FOLLOWING:
2. PROVIDE AND INSTALL (2) NEW CIRCUIT SETTERS AND (1) MIXING VALVE AT THE EXISTING DOMESTIC WATER
HEATERS
PER THE CONTRACT DOCUMENTS.
3. PROVIDE SURVEY OF EXISTING HOT WATER RECIRCULATION PUMPS TO DETERMINE IF EXISTING PUMPS CAN
MEET
DEMAND OF SYSTEM.
4. RE-BALANCE HOT WATER SYSTEM TO FIGURES SHOWN ON CONTRACT DOCUMENTS. LIMBACH EW Parent award context Parent award agency: General Services Administration · Public Buildings Service Parent award NAICS: 238220 Parent award performance state: MI Parent award description: 985 WATER TANK REPLACEMENT AND COOLING TOWER SWEEPING PROJECT, 985 MICHIGAN AVENUE, DETROIT, MICHIGAN. View parent award on USAspending | — | $1,237,991 | Jul 22, 2024 | — – — |
Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.
Government-sourced data comes from SAM.gov, SBA and USAspending.gov and is attributed to its source. Items marked company-reported were provided by the company and are verified by FedSub only where labeled. FedSub is a private company and is not affiliated with SBA, GSA/SAM.gov, or any government agency.