| Subcontractor | Department of Defense | MOBILIZE TO THE SITE.
2. PROVIDE WALL SLEEVES TO THE FOUNDATION CONTRACTOR FOR THE SLEEVES THRU THE FOUNDATION WALL FOR THE 20” DIP DISCHARGE, 8” DIP SUCTION, AND 4” DRAIN LINE.
3. STUB UP 20” DIP DISCHARGE PIPING TO APPROXIMATELY 8FT ABOVE TANK FLOOR LEVEL AND TERMINATE APPROXIMATELY 10FT OUTSIDE TANK FOUNDATION.
4. STUB UP 8” DIP SUCTION PIPING TO APPROXIMATELY 8FT ABOVE TANK FLOOR AND TERMINATE APPROXIMATELY 10FT OUTSIDE TANK FOUNDATION.
5. FURNISH AND INSTALL THE 4” FLOOR DRAIN AND 4” DIP DRAIN PIPING AND TERMINATE APPROXIMATELY 10FT OUTSIDE THE TANK FOUNDATION.
6. PRESSURE TEST THE 20” AND 8” PIPING PER THE SPECIFICATIONS.
7. INSTALL 20” DIP AND C-900 PVC FIRE WATER PIPING AND TERMINATE THE PIPING AT THE 20” MJ 45 @ STA 10+58.06. PRESSURE TEST THIS SECTION PIPING PER THE SPECIFICATIONS.
8. INSTALL (1) 8” DIP OUTSIDE THE TANK FOUNDATION. INSTALL APPROX. 120 FEET OF 8” DIP SUCTION PIPING. PIPING WILL TERMINATE @ STA 10+41.41 ( 8” MJ 45 ELBOW. PRESSURE TEST THIS SECTION OF PIPE AND TIE-IN TO 8” WATERLINE COMING FROM BRUNSWICK COUNTY PER THE PLANS.
9. INSTALL (1) 8” PRESSURE REDUCING / BACKFLOW PREVENTION VALVE VAULT AS SHOWN ON THE DRAWINGS. INSTALL VALVE VAULT, ALL INTERNAL PIPING, VALVE VAULT LID . ALL INTERNAL PIPING WILL RECEIVE (2) COATS OF PAINT.
10. INSTALL (1) 8” FLOW METER VALVE VAULT AS SHOWN ON THE DRAWINGS. INSTALL VALVE VAULT, ALL INTERNAL PIPING, VALVE VAULT LID . ALL INTERNAL PIPING WILL RECEIVE (2) COATS OF PAINT.
11. FURNISH AND INSTALL ALL PIPING AND PUMPS INSIDE THE COMPOSITE TANK. PIPING TO START AT 20” FLG GV, INCLUDE BOTH PUMPS, 8” FLG PIPING ETC. PIPING TO BE INSTALLED AFTER THE FLOOR IS POURED AND THE COMPOSITE TANK IS ERECTED. REQUIRES ACCESS DOORS LARGE ENOUGH FOR A SMALL FORK- LIFT TO ENTER THE TANK FOR THE INTERNAL PIPING ERECTION.
12. FURNISH AND INSTALL THE OVERFLOW PAD AND ASSOCIATED DIP PIPING.
13. FURNISH THRUST BLOCKING ON ALL UNDERGROUND PIPING. SVI-2319048-ACS Parent award context Parent award agency: Department of Defense · Department of the Army Parent award NAICS: 237110 Parent award performance state: NC Parent award description: MOTSU FIRE PROTECTION 750,000 GALLON ELEVATED STORAGE TANK View parent award on USAspending | — | $1,847,523 | Oct 18, 2022 | — – — |
Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.
Government-sourced data comes from SAM.gov, SBA and USAspending.gov and is attributed to its source. Items marked company-reported were provided by the company and are verified by FedSub only where labeled. FedSub is a private company and is not affiliated with SBA, GSA/SAM.gov, or any government agency.