| Role | Agency | Description | Vehicle | Obligated | Action date | Period |
|---|---|---|---|---|---|---|
| Prime | Department of the Interior Bureau of Reclamation | LOWER PARADOX GATE REFURBISHMENT | 140R3019D0013USAspending | $1,609,674 | Sep 18, 2026 | Sep 19, 2023 – Jan 8, 2027 |
| Prime | Department of the Interior Bureau of Reclamation | ANDERSON RANCH DAM TURBINE MODERNIZATION AND RUNNER REPLACEMENT. | — | $16,571,097 | Sep 17, 2026 | Jun 12, 2023 – Jul 4, 2027 |
| Prime | Department of the Interior Bureau of Reclamation | GRAND COULEE JOHN W. KEYS III PUMP-GENERATING PLANT EXCITATION SYSTEM, GOVERNOR, AND PROTECTIVE RELAY REPLACEMENT AND CONTROLS MODERNIZATION, COLUMBIA BASIN PROJECT, WASHINGTON | — | $34,589,808 | Sep 16, 2026 | Apr 12, 2019 – Sep 2, 2028 |
| Prime | Department of the Interior Bureau of Reclamation | MT-CF POWERPLANT GENERATOR 1 TASK ORDER | 140R6021D0003USAspending | $2,252,200 | Sep 9, 2026 | Sep 14, 2021 – Dec 31, 2027 |
| Prime | Department of the Interior Bureau of Reclamation | FURNISH VARIOUS COMPONENTS UNDER IDIQ 140R6021D0003 | 140R6021D0003USAspending | $2,308,600 | Sep 9, 2026 | Sep 14, 2021 – Dec 31, 2027 |
| Prime | Department of the Interior Bureau of Reclamation | MT-CF POWERPLANT GENERATOR TASK ORDER 3 | 140R6021D0003USAspending | $1,898,300 | Sep 9, 2026 | Jun 18, 2024 – Jul 30, 2025 |
| Prime | Department of the Interior Bureau of Reclamation | PARADOX GATE REFURBISHMENT | 140R3019D0013USAspending | $1,194,907 | Aug 12, 2026 | Sep 22, 2022 – Aug 31, 2026 |
| Prime | Department of Defense Department of the Army | RS KERR TURBINE & GENERATOR REHABILITATION | — | $92,187,676 | Jul 22, 2026 | Sep 10, 2021 – Jul 22, 2029 |
| Prime | Department of Defense Department of the Army | UNITS 1-2 GENERATOR STATOR REWIND, BEAVER POWERHOUSE. COMPLETION DUE 705 CALENDAR DAYS AFTER NTP. | — | $20,156,744 | Jun 12, 2026 | Oct 1, 2021 – Jun 12, 2025 |
| Prime | Department of Defense Department of the Army | REHABILITATION OF OLD HICKORY TURBINE GENERATORS | — | $91,728,479 | Jun 10, 2026 | Feb 2, 2023 – Oct 5, 2030 |
| Prime | Department of the Interior Bureau of Reclamation | TASK ORDER - INSTALLATION AND FIELD TESTING OF THE GENERATOR STATOR CORE AND ARMATURE WINDING | 140R6021D0003USAspending | $1,863,000 | May 21, 2026 | Dec 7, 2022 – Jun 30, 2024 |
| Prime | Department of the Interior Bureau of Reclamation | CF POWERPLANT GENERATOR DELIVERY ORDER 2 | 140R6021D0003USAspending | $1,630,700 | May 21, 2026 | Dec 5, 2022 – Sep 15, 2024 |
| Prime | Department of Defense Department of the Army | BARKLEY POWER PLANT TURBINE GENERATOR REHABILITATION FOR UNITS 1-4. | — | $80,356,567 | May 15, 2026 | Sep 29, 2020 – Sep 15, 2027 |
| Prime | Department of Defense Department of the Army | MNA SERVICE STATION UNITS UPGRADE | — | $15,221,649 | Apr 20, 2026 | Apr 7, 2021 – May 20, 2025 |
| Prime | Department of the Interior Bureau of Reclamation | BUSHINGS FOR KA3A KA5A GSU TRANSFORMERS | 140R3019D0013USAspending | $464,725 | Jan 15, 2026 | Sep 6, 2024 – Feb 28, 2026 |
| Prime | Department of Defense Department of the Army | IGF::OT::IGF JOHN DAY BLH TURBINE HUB UPGRADES | — | $24,423,354 | Sep 19, 2025 | Jun 17, 2016 – Nov 26, 2025 |
| Prime | Department of Defense Department of the Army | KEYSTONE POWER PLANT GENERATOR REWIND | — | $13,584,869 | Aug 5, 2025 | Jun 1, 2021 – Jan 29, 2025 |
| Prime | Department of the Interior Bureau of Reclamation | HOOVER DAM GENERATING UNIT A5 RE-WEDGE | 140R3019D0013USAspending | $1,242,403 | Jul 22, 2025 | Sep 4, 2024 – Dec 31, 2025 |
| Prime | Department of the Interior Bureau of Reclamation | CONSTRUCTION AND DELIVERY OF DRAFT TUBE BULKHEAD | 140R3019D0013USAspending | $919,708 | Jun 21, 2025 | Sep 12, 2023 – May 30, 2025 |
| Prime | Department of the Interior Bureau of Reclamation | MT. ELBERT REHABILITATION, UNIT #1&UNIT #2 SHAFT SEAL REPLACEMENTS | — | $1,443,739 | Apr 2, 2025 | Oct 1, 2020 – Jul 31, 2024 |
| Prime | Department of Defense Department of the Army | THE REQUIRED W ORK IS TO PROVIDE MATERIALS, EQUIPMENT AND SERVICES TO REW IND THE GENERATORS OF UNITS 1, 2, AND 3 AT WEBBERS FALLS POWERPLANT. THIS WORK INCLUDES, BUT IS NOT LIMITED TO, THE FOLLOWING: 1) DESIGN, MANUFACTURE, SHOP TEST, AND DELIVER THREE COMPLETE SET OF STATOR COILS 2) DISASSEMBLE THREE GENERATOR UNITS 3) REMOVE OLD STATOR COILS 4) INSTALL AND TEST THREE NEW STATOR WINDINGS AND 5) REASSEMBLE GENERATORS, INSTALL, AND PERFORM FIELD TEST. | — | $6,051,849 | Jul 19, 2024 | Dec 10, 2010 – Jul 20, 2020 |
| Prime | Department of the Interior Bureau of Reclamation | G22, G23, AND G24 OVERHAUL, GRAND COULEE DAM, THIRD POWERPLANT, WASHINGTON. TOTAL AMOUNT OF PROJECT: $101,971,541.00. | — | $149,212,483 | Jun 20, 2024 | May 6, 2011 – Nov 21, 2021 |
| Prime | Department of the Interior Bureau of Reclamation | A9 TURBINE OVERHAUL | 140R3019D0013USAspending | $2,710,595 | Nov 2, 2023 | May 25, 2021 – Nov 25, 2023 |
| Prime | Department of the Interior Bureau of Reclamation | MT - CF PP GENERATOR DELIVERY ORDER 3 | 140R6021D0003USAspending | $1,653,900 | Aug 24, 2023 | Aug 24, 2023 – Aug 19, 2024 |
| Prime | Department of Defense Department of the Army | HIPASE EXCITER LIFE EXTENSION KIT | — | $576,100 | Apr 10, 2023 | Jul 21, 2022 – Sep 30, 2023 |
| Prime | Department of Defense Department of the Army | 200508!500781!96CE!W9127S!USA ENGINEER DIST LITTLE ROCK !W9127S05C0013 !A!N! !N! ! !20050503!20120930!807792031!300989654!301716494!N!VA TECH VOEST MCE CORP !10715 DAVID TAYLOR DR !CHARLOTTE !NC!28262!00000! !AU!* !* !AUSTRIA !+000001500000!N!N!000117330595!2830!WATER TURBINES&WATER WHEELS&COMPS !C9E!ALL OTHER SUPPLIES AND EQUIPMENT !000 !* !333611!E! !3! ! ! ! ! !20200930!B! ! !A! !A!Y!K!2!006!B! !Z!N!F!B!AU!N!L!N! ! ! ! ! !A!A!000!A!B!N! ! ! ! ! ! !0001! ! | — | $108,844,196 | Sep 7, 2022 | May 3, 2005 – Sep 15, 2018 |
| Prime | Department of Defense Department of the Army | EXCITATION SYSTEM | — | $2,720,374 | Dec 21, 2021 | Mar 15, 2018 – Apr 10, 2022 |
| Prime | Department of Defense Department of the Army | FUNDING IS FOR HYDRAULIC TURBINE MODEL FABRICATION. AWARD IS FOR THE PURCHASE OF TWO TURBINE RUNNERS INCLUDING TWO UNIT REWINDS AT HILLS CREEK DAM IN OREGON. | — | $17,595,897 | Nov 22, 2021 | Dec 27, 2010 – Dec 23, 2015 |
Contract vehicles are shown only when present in the source record. Linked award numbers and vehicles open the authoritative record on USAspending.gov.
Agencies supported
- Department of the InteriorGov-sourced
- Department of DefenseGov-sourced
Government-sourced data comes from SAM.gov, SBA and USAspending.gov and is attributed to its source. Items marked company-reported were provided by the company and are verified by FedSub only where labeled. FedSub is a private company and is not affiliated with SBA, GSA/SAM.gov, or any government agency.